Error - Task cannot be indented because linked to engagement milestone
When indenting a task you may receive the following error. Task(s) cannot be indented because it would result in a parent task that is linked to one or more engagement milestones.
This error is thrown because you have a milestone task that is linked to a billing milestone. A task underneath it cannot be indented. Reason being, that would make the milestone task a parent and subject to % complete measurements. As milestone tasks are binary, either done or not done, we don't allow % complete.
Create a New Parent Task
Use a different for the child.
Solution 1
- Original Task
- New Parent Task
- New Task
Remove the Billing Milestone
Go to the Engagement Contract tab and remove the task from the associated milestone.